Water well works have been completed

Important announcement‼️

The water well works we started about 6 months ago in Çatalköy have been completed as of today, and water will start flowing into the tanks of houses in our region within 3 days.

The excavation work, which started on May 30, 2024, lasted 50 days. As a result of the measurements, a water well with a capacity of 70 cubic meters per hour was identified and brought to our region after long and dedicated efforts.

The cost of the well, which was fully financed by our municipality:

Opening the excavation road and preparing the platform: 360,000 TL

Fuel for working machines and generators: 245,953.16 TL

Vehicle maintenance and repair: 4,000 TL

Municipal staff overtime: 27,325 TL

Electrical transformer cost: 577,327.74 TL

Other expenses: 47,317.25 TL

The total cost amounted to 1,261,923.15 TL.

This work has proven that beautiful things can be achieved if given the opportunity.

We would like to thank the Geological Mining Department, Çatalköy Esentepe Municipality employees, and Kyrenia Water Department staff.